I Don't Just Sell Parts. I Run Projects.
How I use project-management thinking to control specifications, samples, production, inspection and delivery for espresso service parts.
PROJECT MANAGEMENT
People ask what I do.
Well...I tell them: I help coffee businesses source maintenance parts from China.
Then they ask: "So you're a trading company?"
No. I'm a project manager who happens to work in coffee parts.
My background isn't coffee. It's project management. I ran telecom projects for European clients. Then I spent two years with a French boss in Zhaoqing who supplied architectural hardware to CRL in the U.S. German-level attention to detail. Japanese-style process discipline.
He taught me one thing:
A purchase order is not a transaction. It's a project.
Here's what that looks like in coffee parts.
Client orders 500 gaskets + 300 shower screens. 30% deposit received.
Clock starts.
Day 0 to 1: Spec lock.
I confirm dimensions, material grade, and packaging in writing. Two things kill gasket orders: wrong hardness (Shore A) and wrong material. If the client's machine needs VMQ silicone and the factory sends NBR rubber, the gasket hardens in 3 months and leaks. Spec gets locked before production.
Day 2 to 3: Material check.
I request the compound batch number and incoming inspection report. For shower screens, I check the steel grade (304 vs generic) and hole count. A stamped screen with burred holes causes channeling — water hits the puck in concentrated jets instead of an even shower.
Day 4 to 7: First article.
First batch comes off the line. I inspect it myself. For gaskets: dimensions, hardness, compression set. For screens: hole uniformity, flatness, edge finish. I send photos and a short video to the client. No mass production until they approve.
Day 8 to 20: Production + in-line QC.
Mass production runs. I visit the factory at least once. Random dimensional checks. The most common failure point here is screen warping. Thin stamped screens can bend during handling or packing. I flag any deviation immediately.
Day 21 to 25: Final inspection + packing.
100% visual inspection. Dimensional sampling against confirmed specs. Gaskets must be installed right-side-up — a flipped gasket leaks even if it's the correct size. Everything labeled by SKU, packed in neutral cartons.
Day 26 to 28: Shipment.
Invoice, packing list, material records. Tracking sent.
Day 30+: Delivery confirmation.
Client confirms fit and quality. If good, next order. Loop closes.
Why this matters?
A gasket that's 0.3mm off leaks. A screen with inconsistent perforation ruins extraction. You can't fix that with a lower price. You fix it with process.I don't compete on price. I compete on predictability.
My old boss used to say: "If you can't describe the process, you don't understand the product."
So here's my process. Written down.